Richmond's Diamond District: What's built, the fights and what's next
Add Axios as your preferred source to
see more of our stories on Google.

The parking garage for Doma, the apartment complex off Slider Way. Photo: Karri Peifer/Axios
After decades of false starts, Richmond finally got its long-promised baseball stadium this year, but the larger $2.4 billion Diamond District redevelopment is far from finished.
Why it matters: The project promises to transform 67 acres into a new neighborhood that will generate tax revenue to help the city repay its ballpark debt.
- But delays and changing plans have pushed much of the original first phase years behind schedule โ and fueled legal battles along the way.
The big picture: An Axios tour last week offered a look at what's finished, what's taking shape and what remains on the drawing board.
- โ Finished: CarMax Park, which opened in April, remains the district's only completed major development.
- ๐๏ธ Under construction: The first apartment complex, Doma; a 453-space parking garage; new streets, utilities and a public park.
- ๐ Still planned: Hotels, offices, restaurants and affordable housing are in various stages of planning and permitting, with construction yet to begin.

Zoom in: Much of the work since spring 2025 has happened underground, with crews installing utilities and other infrastructure, says Maritza Pechin, director of development for Thalhimer Realty Partners, the Richmond firm leading the redevelopment.
- At 67 acres, the district is nearly 40% the size of Scott's Addition, Pechin tells Axios.

What they're saying: "The full build-out will take 15 years, and Phase 1A is the foundation," Pechin says. "What happens in Phase 1A sets the tone for everything that comes after, so we're focused on getting it right."
Yes, but: The slow progress has financial implications for Richmond.
- The city borrowed nearly $130 million to build CarMax Park.
- The longer the neighborhood takes to materialize, the longer the city waits for the revenue expected to help repay that debt.

โพ How the deal changed
Richmond's Diamond District deal looks very different from the one city leaders pitched four years ago.
- How we got here:
โพ๏ธ 2022: The original pitch. Then-Mayor Levar Stoney selects RVA Diamond Partners to build a new baseball stadium for the Flying Squirrels and surrounding neighborhood.
- The first phase promised more than 1,200 homes, a hotel, retail, parking and parks by 2026.
- The stadium would be publicly financed, but the city wouldn't put its credit on the line. The developer and future property owners would cover any shortfall in the revenue expected to repay the debt.
๐ 2023: The deal hits trouble. Rising interest rates complicated the financing, and the stadium opening was pushed back a year to 2026.
- Disagreements over the ballpark's cost and design grew so contentious that Major League Baseball stepped in to help mediate.
๐ฐ 2024: Richmond overhauls the deal. The city put its own credit behind nearly $130 million in stadium bonds and borrowing another $33.7 million through its Economic Development Authority for infrastructure.
- The key change: Richmond is now responsible for repaying the stadium bonds even if development-generated revenue falls short.
- The Squirrels took over stadium construction, while the original development partnership splintered. Thalhimer emerged as the lead developer of the surrounding neighborhood.
2025: Construction gets underway โย slowly. The EDA sold the first 18 acres to the developer for $11.4 million in March โ about six months behind schedule.
- Infrastructure work began that spring, but construction on the first apartments, hotel and retail spaces remained stalled.
2026: Construction โย and more changes. CarMax Park opened in April and construction finally began on the first apartments in July.
- Richmond also tapped another $14.7 million in reserves to help the EDA buy the former Sports Backers Stadium property from VCU.
And the plans are still changing: In October, the EDA approved revisions to Phase 1A, trading some market-rate apartments for more commercial space and hotel rooms.


What they're saying: "We're building more, not less," Pechin tells Axios about the most recent changes.
- Pechin says more offices and hotel rooms will help attract people to the district even when there's no baseball game.
Between the lines: Jason Guillot, who leads the development group, told the EDA the changes would generate more tax revenue for Richmond than the original, more residential-heavy plan, per BizSense.
Yes, but: With the full development expected to take roughly 15 years, much of the neighborhood's ultimate makeup remains subject to market conditions โ and could change again.

โพ Food fights and other Diamond District drama
Meanwhile, for the Squirrels, opening their long-awaited ballpark this spring was supposed to be a triumph.
Why it matters: Instead, the team's inaugural season at CarMax Park unfolded amid ongoing construction, business disputes and an increasingly bitter relationship with the city and developers.
The biggest fight: In September, the Squirrels' ownership group sued Richmond, its EDA and Diamond District developers, alleging fraud, broken promises and lost revenue tied to the delayed redevelopment, per BizSense.
- Among the flash points: A parcel next to CarMax Park's entrance that the team alleges was supposed to become a noncompeting, minority-owned food hall.
- Instead, Thalhimer leased space for restaurants, including a sports bar the Squirrels say will compete with stadium concessions.
The other side: The city and EDA are seeking dismissal, arguing the claims lack legal merit and the Squirrels failed to follow required dispute resolution procedures.
- They also say the team's prolonged negotiations with VCU contributed to construction delays, per BizSense.
What they're saying: Despite a record-breaking inaugural season at CarMax Park, the Squirrels say they're disappointed the surrounding development hasn't materialized as promised.
- "We are hopeful that our lawsuit will compel the EDA, the City, and Diamond District Partners to honor their promises and obligations to the Squirrels and the people of Richmond," team spokesperson Ben Sosenko tells Axios.

Meanwhile, two other legal fights have been settled in recent weeks:
- A defamation suit stemming from an opening night confrontation between Guillot and Flying Squirrels owner Lou DiBella, per the Times-Dispatch
- A two-year dispute among the original Diamond District development partners, per BizSense
Another sticking point: VCU and the Squirrels still haven't reached an agreement to share CarMax Park, despite the EDA signing a lease with the university.
- The deadline for that agreement was extended to Dec. 31.
- VCU is expected to play its 2027 season at the old Diamond โ delaying demolition and redevelopment of that land.
What they're saying: "We continue to work with all parties to secure VCU Baseball's long-term home," VCU spokesperson Brian McNeill said in a statement to Axios last week.

๐ What's next
Enough about what went wrong. Here's what's next for the Diamond District.
Why it matters: The next two years are expected to bring the first major additions beyond CarMax Park.

Coming in 2027:
- ๐ฆ New streets: Four roads โ Encore Avenue, Rally Road, Diamond View Drive and Slider Way โ plus two signalized intersections are expected to open.
- ๐ณ A new park: More than 2 acres of public green space, including a playground, event lawn and walking connections should open by year's end.
- ๐จ Public art: Richmond artist Mickael Broth is designing a landmark sculpture for the park. Richmonders can weigh in through Dec. 3.
- ๐๏ธ More construction: Work is expected to begin on a 115,000-square-foot office building, restaurants, retail, and a 146-room Tapestry Collection by Hilton hotel.

Coming in 2028:
- ๐ช The first residents: Doma, the 276-unit apartment building now under construction, is expected to welcome tenants in the first quarter.
- ๐ Restaurants: The Gateway Retail building, planned for Makers Union and a sports bar from Richmond-based Eat Restaurants Partners โ is targeted for completion in spring 2028. Restaurant opening dates haven't been announced.
- ๐ข Offices: A new building anchored by Richmond law firm Hirschler is expected to be completed in the fall.

Still TBD:
- Affordable housing: A 161-unit development for households earning 60% or less of the area median income is in design and permitting, with no confirmed opening date.
- Hotels: An opening date hasn't been confirmed for the Tapestry hotel, and the planned second hotel's operator and timeline have yet to be announced.
- The old Diamond: Demolition remains unscheduled, with VCU expected to play there in 2027 and funding still unresolved.
The bottom line: By this time next year, Richmonders could have new streets and green space. But it'll likely be more than a year before the district begins feeling like a neighborhood.